|
Coping With Risk
by Mary Sakry
If your project (software product or process
improvement effort) is plagued with problems, you
might need effective risk management.
Risk management is similar to performing
preventive health care and buying insurance for
your project. It involves identifying potential
problems (risks), analyzing those risks, planning
to manage them, and reviewing them.
On the last page of this newsletter, we have
provided you with a copy of our risk process. It is
simple, effective and takes 60 to 90 minutes.
Risk Identification
To identify risks, we must first know what one
is. When people begin performing risk management,
they often start by listing known problems. Known
problems are not risks. Risks are
potential problems. During
risk identification you might notice some known
problems. If so, just move them to your current
problems list. Then concentrate on future potential
problems.
Risk identification can be done using a
30-minute brainstorming session. Be sure to invite
anyone who can help you think of risks. Be creative
and invite the project team, customers, people who
have been on similar projects, and experts.
Example risks are: "We may not have the
requirements right," "The technology is untested",
"Key people might leave," "Their server won't
restart in situation X," "People might resist the
change." Any potential problem or critical project
feature is a good candidate for the risk list.
Risk Analysis
The purpose of analysis is to set priorities and
determine where to focus the risk mitigation
efforts. Some of the identified risks are unlikely
to occur and others might not be serious enough to
worry about. During analysis, you will discuss each
risk item to understand how devastating it would be
if it did occur and how likely it is to occur. Most
people use a rating system (see process) to help
select the most important ones to work on.
For example: if you discussed the risk of a key
person leaving, you might decide that it would have
a large impact on the project, but that it is not
very likely. The risk items that have a high
likelihood and a high impact will typically be the
ones to select.
Risk Management Plan
There are two things one can do to manage risk.
The first is to take action to reduce (or partially
reduce) the likelihood of the risk occurring. For
example, some part-time process improvement teams
make their deadlines earlier and increase their
efforts to minimize the likelihood of team members
being pulled off the project due to changing
organizational priorities. In a software product, a
critical feature might be developed first and
tested early.
Second, we can take action to reduce the effect
if the risk does occur. Sometimes this is an action
prior to the crisis, such as the creation of a
simulator to use if the hardware is late. At other
times it is a simple backup plan such as running a
night shift to share hardware.
For the potential loss of a key person, for
example, we might do either of two things: 1) We
could plan to reduce the impact by making sure
other people become familiar with that person's
work or 2) To reduce the likelihood of attrition,
we could give the person a raise, or provide
daycare.
Risk Review
You will want to review your risks periodically
so you can check how well mitigation is
progressing. You can also see if the risk
priorities need to change or if new risks have been
discovered. You might decide to rerun the complete
risk process if significant changes have occurred
on the project. Many people incorporate risk review
into other regularly scheduled project reviews.
Risk Management Process
1. Determine scope of the risk
session.
2. Select the team and
moderator.
The moderator explains the risk process
to new team members.
3. Identify
risks (potential future problems)
4. Analyze risks.
- For each risk item:
- Does the team understand the risk item?
-If necessary, split into separate risk
items, e.g.,
- Discuss and determine its scope;
- What would the consequences be if this
risk item did happen?
- Determine what the
impact would be if the worst
happened, using a scale of one to ten.
- Determine how likely it
is that the risk item will occur, using a
scale of one to ten.
- Determine the priority
of the risk items and thus which to work on
(impact vs. likelihood)
5. Plan to mitigate risks.
- Select the most important risk issues, such
as the top two or three, or top 20%.
- Brainstorming on actions that could be taken
to reduce the likelihood of the
risk item occurring.
- Decide which actions to pursue.
- Select a person to be responsible for each
action chosen.
- Document the information in the risk
management plan.
6. Review risks.
(C) 1998, The Process Group, All rights
reserved.
Top of newsletter
|